MECH/PLUMB-20-0063 Mechanical/Plumbing -Residential
Address:
228 Stone Gate Ln
Eastsound,  WA  98245
Parcel #: 271314011000
Status: Closed
Submitted: 5/14/2020
Approved: 5/29/2020
Issued: 6/3/2020
Closed: 6/30/2020
Expires: 6/30/2021
Inspections:
Required: 1
Complete: 1
Total Fees:
$6900
Additional fees may be required
Project: ROOF TOP PV SYSTEM

Contacts
OWNER:
ORCAS SERENDIPITY LLC
APPLICANT:
ORCAS SERENDIPITY LLC
CONTACT:
WOLFE, JUSTIN

Contractors
EC:
RAINSHADOW SOLAR/ERGY SOLS INC
License #: RAINSSS837NT

Details
Please enter the following details about your project.

Parcels
Parcel Owner Address
271314011000 ORCAS SERENDIPITY LLC 228 Stone Gate Ln
Eastsound,  WA 98245

Submittals
The submittals listed below are standard for all permits of this type.  To upload submittal items, click the BLUE "0 Files" link on the far right of the submittal item. Please upload documents in PDF format. Be sure that all plans are to scale and legible. Applications can be found here: https://sanjuanco.com/981/Building-Permit-Applications ITEMS THAT ARE DEFERRED ARE NOT INITIALLY REQUIRED, BUT YOU MAY UPLOAD THIS INFORMATION IF APPLICABLE, OR REQUESTED LATER. NOT ALL PERMITS REQUIRE ALL SUBMITTAL ITEMS.
Submittal Required Received Accepted
Completed Permit Application Yes 5/14/2020 5/14/2020
Plan to include address or TPN, name of owner; driveway location to the right of way, all existing & proposed structures and elements with dimensions and distances from each other and property lines. Yes 5/14/2020 5/14/2020
Manufacturer's specifications and installation instructions: provide a copy of the specifications and installation instructions for gas appliances, furnaces and wood/pellet/stove/gas fireplace/insert (2 copies) Yes 5/14/2020 5/14/2020

Approval Steps
These permit workflow steps reflect the most current updated status and are linked directly to the permit software used by County staff.
Step Status Date
Intake Complete 5/14/2020
Critical Area Review Approved 5/19/2020
Archaeology Review Approved with Conditions 5/19/2020
Building Plan Review Approved with Conditions 5/29/2020

Reviews
Start Complete Applicant Response

Fixtures
Fixture Quantity Per Unit Value
Roof Mount PV System 1 $12.00 $12.00
Total: $12.00

Valuations
Valuations are based on the total cost associated with construction of the project, including labor and materials. Site work such as septic systems and the land cost are not included in the valuation. Valuation and fees will be validated during the review process.
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee Amount
Minimum Mechanical/Plumbing Fee $69 $69.00
Total : $69.00

Bonds
Type Number Amount Issued Expires Completed

Inspections
Inspections are conducted on Mondays, Tuesdays and Thursdays. Inspections are scheduled by number, by inspector, and posted online, after 9am the morning of the inspection. *Due to recent Virus concerns please do not call for inspections if you are ill, or have been exposed to someone that is. Call 360.370.7578 for possible Skype inspection alternatives, or schedule a remote inspection here: https://www.sanjuanco.com/FormCenter/Community-Development-6/VIRTUAL-Inspection-Request-Planning-and--69
Completed On
Final - Mech/Plumb 6/30/2020

Structures
Structure Use Occupancy Type Square Footage

Conditions
Any equipment and/or appurtenances not shown on this approved site plan (i.e. mechanical equipment, retaining walls, decks, etc.) are not approved. Revisions to plans must be submitted to DCD for approval prior to installation.
Fuel tank >125 gallons must be setback at least 10 feet from all property lines and structures.
All propane tanks and trenching for propane lines must be setback five (5) feet from all on-site sewage system (OSS) components.
Address must be posted and visible from the street.
Underground exterior fuel line must be sleeved and a trace wire installed. Do not cover until inspected.
Pressure test of interior and exterior fuel lines must be witnessed by inspector.
The Inadvertent Discovery Plan (IDP) shall be kept on the job site and followed if any cultural material (e.g., bones, shell, antler, horn, or stone tools) and/or human remains are found.
Approved plans shall not be changed, modified or altered without authorization from the Department of Community Development (DCD). Revisions shall be submitted and approved by DCD prior to inspection.
Electrical Work. If electrical work is proposed, a separate electrical permit is required. You can contact L&I at 360-416-3000 for information on how to obtain an electrical permit. Electrical systems must be inspected by L&I prior to requesting a framing inspection and final approval granted by L&I prior to requesting a final building inspection from DCD.
Reinspection fee: All approved construction plans, the approved site plan, the printed building permit, and the permit inspction placard are required to be on-site for inspection purposes, and work to be inspected shall be complete and ready for inpsection. If an inspection is called for and palns are not available on site, or the work is not ready for inspection, or if previously identified corrections have not been made, approval will not be granted. In addition, a re-inspection fee will be charged and must be collected by DCD prior to any further inspections being performed or approvals granted.
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the work is commenced. The building official is authorized to grant, in writing, extension of time, for a period of one 180 days. The extension shall be requested in writing and justifiable cause demonstrated.
Building permits must be renewed annually until final inspection and occupancy has been granted.
Pressure test of interior and exterior water supply lines must be witnessed by inspector.
Any assistance of any person(s) to provide labor, materials and/or assistance on any aspect(s) of the construction, alteration or repair authorized by the building permit, the aggregate compensation for which equals or exceeds $500 shall be conducted by contractor(s) registered and currently licensed under the laws of the State of Washington.
Applicant shall phone 1-800-424-5555 (24 hour Utility Location Center) to Locate Utilities prior to excavation. San Juan County will not accept any responsibility on behalf of applicants failing to comply with the requirement to contact the appropriate utility companies. Any resultant action for failure to perform, inlcuding action necessary to make corrections or prevent liability to the county will be the sole responsibility of the owner, permit applicant, or authorized agent as noted herein.

Required Permits
Type Requirement For Number Status

Notes
Project Notes

Associations