Contact
BUILDG-18-0152 New Single Family Residence
Address:
341 LIGHTHOUSE LN
FRIDAY HARBOR,  WA  98250
Parcel #: 240853037000
Status: Closed
Submitted: 5/30/2018
Approved: 8/17/2018
Issued: 8/20/2018
Closed: 7/1/2020
Expires: 8/20/2020
Inspections:
Required: 8
Complete: 21
Project: NEW SFR & GARAGE

Public Notice

Contacts
OWNER:
ROBISON/KANE, DAVID/DONALD
INSPECTION CONTACT:
PETER C SCHMIDT CONST INC
APPLICANT:
ROBISON/KANE, DAVID/DONALD

Contractors
CC:
PETER C SCHMIDT CONST INC
License #: PETERCS990PE

Details
Please enter the following details about your project.

Parcels
Parcel Owner Address
240853037000 DONALD SCOTT KANE & DAVID FEINER ROBISON San Juan County
UNKNOWN,  WA 98250

Submittals
The submittals listed below are standard for all permits of this type.  To upload submittal items, click the BLUE "0 Files" link on the far right of the submittal item. Please upload documents in PDF format. Be sure that all plans are to scale and legible. Applications can be found here: https://sanjuanco.com/981/Building-Permit-Applications ITEMS THAT ARE DEFERRED ARE NOT INITIALLY REQUIRED, BUT YOU MAY UPLOAD THIS INFORMATION IF APPLICABLE, OR REQUESTED LATER. NOT ALL PERMITS REQUIRE ALL SUBMITTAL ITEMS.
Submittal Required Received Accepted

Approval Steps
These permit workflow steps reflect the most current updated status and are linked directly to the permit software used by County staff.
Step Status Date

Reviews
Start Complete Applicant Response

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuations are based on the total cost associated with construction of the project, including labor and materials. Site work such as septic systems and the land cost are not included in the valuation. Valuation and fees will be validated during the review process.
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee Amount
Total : $56.00

Bonds
Type Number Amount Issued Expires Completed

Inspections
Inspections are conducted on Mondays, Tuesdays and Thursdays. Inspections are scheduled by number, by inspector, and posted online, after 9am the morning of the inspection. *Due to recent Virus concerns please do not call for inspections if you are ill, or have been exposed to someone that is. Call 360.370.7578 for possible Skype inspection alternatives, or schedule a remote inspection here: https://www.sanjuanco.com/FormCenter/Community-Development-6/VIRTUAL-Inspection-Request-Planning-and--69
Completed On
SHEAR WALLS EXT. 1/17/2019
Foundation - Setbacks, Stormwater, Footings, Stemwall, monopour, slab, or piers 10/18/2018
FOOTING 9/25/2018
FUEL TANKS 8/8/2019
EROSION CONTROL 8/15/2019
SHEAR WALLS EXT. 1/3/2019
Foundation - Setbacks, Stormwater, Footings, Stemwall, monopour, slab, or piers 11/8/2018
FOOTING 11/8/2018
EROSION CONTROL 8/8/2019
SETBACKS 9/25/2018
EXT. GAS PIPING 3/12/2019
PIER/COLUMN/POSTHOLES 8/15/2019
ROOF NAILING 8/15/2019
Ceiling Insulation: R-38 (single joist vaulted) or R-49 (truss) 5/10/2019
Insulation: WALL, FLOOR and/or SLAB, CEILINGS, GLAZING 5/10/2019
Glazing: U 0.30 5/10/2019
Rough-in plumbing 5/10/2019
Rough-in Mechanical 5/10/2019
Framing- L&I Approval 5/10/2019
Final 7/1/2020
Final Occupancy 7/1/2020

Structures
Structure Use Occupancy Type Square Footage

Conditions

Required Permits
Type Requirement For Number Status

Notes
Project Notes
CoO 7/1/2020

Associations