BUILD-19-0253 Remodel, Additions- Residential
Address:
32 Haven Rd
Eastsound,  WA  98245
Parcel #: 271460048000
Status: Issued
Submitted: 9/24/2019
Approved: 12/13/2019
Issued: 1/28/2020
Closed:
Expires: 6/30/2021
Inspections:
Required: 17
Complete: 1
Total Fees:
$2,61250
Additional fees may be required
Project: REMODEL

Public Notice

Contacts
OWNER:
FISHING BAY LLC
APPLICANT:
FISHING BAY LLC

Contractors
CC:
C A REED CONST
License #: CREEDRC845RF

Details
Please enter the following details about your project.

Parcels
Parcel Owner Address
271460048000 FISHING BAY LLC 32 Haven Rd
Eastsound,  WA 98245

Submittals
The submittals listed below are standard for all permits of this type.  To upload submittal items, click the BLUE "0 Files" link on the far right of the submittal item. Please upload documents in PDF format. Be sure that all plans are to scale and legible. Applications can be found here: https://sanjuanco.com/981/Building-Permit-Applications ITEMS THAT ARE DEFERRED ARE NOT INITIALLY REQUIRED, BUT YOU MAY UPLOAD THIS INFORMATION IF APPLICABLE, OR REQUESTED LATER. NOT ALL PERMITS REQUIRE ALL SUBMITTAL ITEMS.
Submittal Required Received Accepted
Completed Permit Application Yes 9/19/2019 9/24/2019
Worksheet showing all impervious surfaces and disturbed areas Yes 9/19/2019 9/24/2019
Address GIS review required for E-911 purposes Yes 9/19/2019 9/24/2019
Right of Way Permit Application -SIGNED by applicant Yes 9/19/2019 9/24/2019
Construction drawings - incl. foundation, framing layout, floor plan, construction details No 9/19/2019 9/24/2019
Profile plan - lot line to lot line include profile, height measurement, and use of all existing and proposed buildings and structures on the site. Yes 9/19/2019 9/24/2019
Engineering - Not all permits require engineering, but when included, it must be shown on the construction drawings. You must show how your project meets minimum Prescriptive building codes, OR be engineered. Yes 9/19/2019 9/24/2019
Signed Septic Verification from the Health Department Yes 9/19/2019 9/24/2019

Approval Steps
These permit workflow steps reflect the most current updated status and are linked directly to the permit software used by County staff.
Step Status Date
Intake Complete 9/24/2019
Cursory Review- Building Complete 12/6/2019
Land Use Review Approved with Conditions 12/6/2019
Critical Area Review Approved 12/6/2019
Archaeology Review Approved with Conditions 12/6/2019
Septic Review Approved with Conditions 9/26/2019
Building Plan Review Approved with Conditions 1/14/2020
Stormwater Review Approved with Conditions 12/13/2019
Address Verification Existing 9/24/2019
Fire Marshal Review Approved with Conditions 12/9/2019

Reviews
Start Complete Applicant Response

Fixtures
Fixture Quantity Per Unit Value
Furnace, Boiler, Air Handler, Oil Heater 1 $20.00 $20.00
Air Conditioner, Heat Pump 1 $20.00 $20.00
Kitchen Hood / Ductwork (Residential) 1 $17.00 $17.00
Exhaust Fans / Ductwork 2 $8.00 $16.00
Gas Appliances/ Outlets 1 $12.00 $12.00
Toilet/ Urinal/ Bidet 1 $11.00 $11.00
Sinks 2 $11.00 $22.00
Shower, Bathtub 2 $11.00 $22.00
Dishwasher 1 $11.00 $11.00
Clothes Washer 1 $11.00 $11.00
Total: $162.00

Valuations
Valuations are based on the total cost associated with construction of the project, including labor and materials. Site work such as septic systems and the land cost are not included in the valuation. Valuation and fees will be validated during the review process.
Valuation Quantity Rate Value
REMODEL 804.00 $64.67  / SQ.FT. $51,994.68
Total: $51,994.68

Fees
Fee Amount
BUILD PLAN REVIEW (DETAILS TAB) $936.00
Plumb Fixtures Fees $77.00
State Surcharge $6.50
Plumbing Base Fee w/ Building Permit $34.00
BUILD FEE (DETAILS TAB) $1,440.00
Mechanical Fixtures Fees $85.00
Mechanical Base Process Fee w/ building permit $34.00
Total : $2,612.50

Bonds
Type Number Amount Issued Expires Completed

Inspections
Inspections are conducted on Mondays, Tuesdays and Thursdays. Inspections are scheduled by number, by inspector, and posted online, after 9am the morning of the inspection. *Due to recent Virus concerns please do not call for inspections if you are ill, or have been exposed to someone that is. Call 360.370.7578 for possible Skype inspection alternatives, or schedule a remote inspection here: https://www.sanjuanco.com/FormCenter/Community-Development-6/VIRTUAL-Inspection-Request-Planning-and--69
Completed On
Setback Inspection 6/30/2020
Stormwater: Construction BMP's in place at start of project
LPG: Exterior Fuel Line(s) (Pressure test to be witnessed)
LPG: Interior Fuel Line(s): (Pressure test to be witnessed)
Shearwalls: (Nailing, hold downs, strapping, per engineered or prescriptive design)
Rough-in Mechanical
Framing- L&I Approval
Rough-in plumbing
Insulation: WALL, FLOOR and/or SLAB, CEILINGS, GLAZING
Ceiling Insulation: R-38 (single joist vaulted) or R-49 (truss)
Glazing: U 0.30
Interior Shear Walls: (per engineered or prescriptive design)
High Efficacy Lighting Compliance Verification
Driveway Inspection
Stormwater Final
Final
Foundation - Setbacks, Stormwater, Footings, Stemwall, monopour, slab, or piers

Structures
Structure Use Occupancy Type Square Footage

Conditions
By signing this application, the applicant affirmatively states that he/she is the (an) owner or an authorized agent of the owner(s).
The Inadvertent Discovery Plan (IDP) shall be kept on the job site and followed if any cultural material (e.g., bones, shell, antler, horn, or stone tools) and/or human remains are found.
Issuance of this building permit automatically conveys to DCD, and/or its authorized agents, the authority to enter the premises at reasonable hours for the purposes of inspecting the project for adherence to the terms of the permit, until such time as the project is complete AND the final inspection is approved.
Effective 4/1/92, per RCW 19.27.095, all building permit applications must include the name, address, and phone number of the office of the lender administering the interim construction financing, if any; or the name and address of the firm that has issued a payment bond on behalf of the prime contractor for the protection of the owner, if the bond is for an amount not less than fifty percent of the total amount of the construction project. (Note that contractors are only required to carry a bond amount of $6,000 in order to be licensed.)
APPLICANT CERTIFIES BY SIGNING THIS APPLICATION THAT HE/SHE WILL PHONE 1-800-424-5555 (24 hour Utility Location Center) TO LOCATE UTILITIES PRIOR TO EXCAVATION* *San Juan County DCD will not accept any responsibility on behalf of applicants failing to comply with the requirement to contact the appropriate utility companies. Any resultant action for failure to perform, including action necessary to make corrections or prevent liability to the county will be the sole responsibility of the owner, permit applicant, or authorized agent as noted herein.
Any assistance of any person(s) to provide labor, materials and/or assistance on any aspect(s) of the construction, alteration or repair authorized by the building permit, the aggregate compensation for which equals or exceeds $500 shall be conducted by contractor(s) registered and currently licensed under the laws of the State of Washington.
At the end of 60 months after issuance of a building permit, if construction has started but is not complete as evidenced by the issuance of a certificate of occupancy, the permit shall expire. To finish work not completed at the time of expiration, a new permit shall be applied for and obtained. The valuation of construction for permit fees shall be the valuation of construction remaining that has not been inspected. The building official may authorize a single 12 month extension of the permit upon review of written request for such extension.
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 1 year after its issuance or if the work authorized on the site by such permit is suspended or abandoned for a period of 1 year after the work is commenced. The building official is authorized to grant, in writing, extension of time, for a period of one (1) additional year. The extension shall be requested in writing and justifiable cause demonstrated.

Required Permits
Type Requirement For Number Status
Sewage Design Application Close
Certificate of Water Availability-Community Water Source Close
Certificate of Water Availability-Alternative Source Close
Certificate of Water Availability - Individual Well Close
Revision - Building No REVISION-20-0018 Issued

Notes
Project Notes

Associations